tin cổ đông
Periodical meeting of PVSB’s Management Board– Quarter III/2014

On 24th October 2014, the periodical meeting for third quarter was held by Management Board of PVSB to pre-evaluate the implementation of first 9 months in 2014 and develop the business plans for 2014 fourth quarter.

Based on the result from first 9 months 2014, Management Board has recognized and highly appreciated the result achieved. Business activities and commercial activities were expanded.  The Company has completedthe construction and finalization of the packages: " Fabrication SVSW Piles and Conductor Piles for South-West Golden Lion Project " , " Clamps manufactured services for the repair of HST’s rig base of HSTD Project " and " Fabrication Service and combination of Upper deck floor of HRD Project” under the contract signed with PTSC -MC

Having completed packages supplying pipes, valve, fitting with the contract value of USD 91,073, and in the progress of implementing two contracts supplying fire pump worth USD 2.389.000 and providing valve  worth USD 74.970 for VSP

No.

Indicator

2014 Plans

2014, 3rdQuarter Actual result 

First 9 months  2014 Actual result 

Completion

(%) 

1

Total Revenue

75,00

19,10

64,71

86%

2

Profit before Tax

0,50

0,42

1,77

354%

3

Profit after Tax

0,39

0,20

1,11

285%

4

Tax and payables to the State

3,39

1,26

3,14

93%

5

Capital investment and facilities procurement

16,86

-

2,74

30%


 

Services
Project
Web links
Weather
City:


Statistic
Online: 81
Visitors: 7482478
Copyright © 2012 Web HP, All Rights Reserved